Supply of all water testing equipment, installation, commissioning, and training for Damavand Petrochemical Complex to support operations of 70,000 cubic meters per hour of cooling water, 32 cubic meters per hour of fresh water, 660 tons per hour of steam, 246 megawatts of electricity, 156 tons per hour of oxygen, and 48,000 normal cubic meters per hour of nitrogen. This petrochemical complex provides utilities (water, electricity, and steam) required for the processing units in the Pars Special Economic Energy Zone (Assaluyeh). The complex’s feedstock includes 610 million cubic meters of natural gas annually, supplied from the South Pars gas field development phases, along with 410 tons per hour of returned condensate water from the surrounding facilities.


Project location: Assaluyeh
Client: Damavand Petrochemical Company
Duration of execution: 3 months